Some projects I've noticed I've documented below.
Frederica-Magnolia Line Replacement
Delmarva Power is replacing the 25kV long hual feeder line between Frederica and Magnolia in Kent County, Delaware. The line work is being done along DE 1 and Clapham Rd.
Centreville Feeder Line Replacement
Delmarva Power is replacing the 1950s 12.5kV feeder between the Centreville Substation and the town of Centreville, Maryland. This project is now complete and also included moving a section of the line due to the construction of a future interchange. This work took place along Tidewater Drive, US 301 and MD 304
Queenstown-Centreville Line Replacement
Delmarva Power has replaced the 25kV line between Queenstown and Centreville, Maryland. The project is now complete and took place along MD 18.
Wye Mills-Queen Anne Line Replacement
Delmarva Power is currently installing a new double circuit 25kV feeder which will run between the Wye Mills Substation and the town of Queen Anne, Maryland. This includes replacing an entire ESPSCo. line. This project is taking place along US 50 and MD 404.
AESO Projects
-
I've found an entire PDF file on transmission projects that have been identified by the Alberta Elec…
-
17 Jan 2016
Western Alberta Transmission Line
-
Altalink recently released a video and what stood out was the fact that they used a gold spacer! ww…
-
23 Dec 2015
See all articles...
Authorizations, license
-
Visible by: Everyone (public). -
All rights reserved
-
52 visits
Jump to top
RSS feed- Latest comments - Subscribe to the feed of comments related to this post
- ipernity © 2007-2024
- Help & Contact
|
Club news
|
About ipernity
|
History |
ipernity Club & Prices |
Guide of good conduct
Donate | Group guidelines | Privacy policy | Terms of use | Statutes | In memoria -
Facebook
Twitter
Sign-in to write a comment.