The former Burilda loop location showing the staff hut, main and loop tracks and the staff exchange platform.Looking south, Up direction, towards Gap.The radio hut and mast will go just past the timber power pole. April 1993.

Comments
 GrahamH
GrahamH club
www.artc.com.au/Article/Detail.aspx?p=6&id=353
15 Nov 2011 ARTC New passing loop at Burilda another boost for Hunter Valley rail corridor

Australian Rail Track Corporation (ARTC) has continued its drive to enhance the efficient movement of coal along the Hunter Valley Coal corridor with the construction of a new passing loop at Burilda, between Werris Creek and Breeza.

The passing loop cost around $13.8 million and involved ARTC constructing new track to accommodate 82 wagon coal trains.

This significant infrastructure project required the installation of 1,520m of track including 60kg rail, digital signal technology and concrete sleepers.

Construction took five months to complete.